1BEFORE THE
FLORIDA PUBLIC SERVICE COMMISSION

In re: Florida Power & Light Company’s ) Docket No: __________

Petition for Issuance of a Storm Recovery ) Filed: January 13, 2006

Financing Order )



FLORIDA POWER & LIGHT COMPANY’S

PETITION FOR ISSUANCE OF A

STORM RECOVERY FINANCING ORDER
Florida Power & Light Company (“FPL” or the “Company”), by its undersigned counsel, respectfully petitions the Florida Public Service Commission (“PSC” or “Commission”) pursuant to Sections 366.04, 366.05, and 366.8260 of the Florida Statutes (2005), Rule 25-6.0143, Florida Administrative Code, and relevant orders of the Commission for entry of a storm recovery financing order substantially in the form attached hereto, or, in the alternative, an order approving the establishment of a storm cost recovery surcharge, and, irrespective of the method of cost recovery implemented, for approval of FPL’s prudently incurred storm-recovery costs related to the 2005 storm season (this “Petition”).

Introduction

Utilities such as FPL are entitled to recover prudently incurred costs to provide electric service. Storm recovery costs are a cost of providing electric service in Florida, but are not reflected in FPL’s base rate charge.1 Thus, storm-recovery costs must be recovered through means other than FPL’s base rate charge. Windstorm insurance coverage, secured on behalf of customers and in the past included as a part of FPL’s cost to provide electric service, was no longer cost-effectively available following Hurricane Andrew in 1992. Pursuant to prior Commission orders and consistent with Rule 25-6.0143, Florida Administrative Code, FPL has established a storm and property insurance reserve (Account No. 228.1) (“Reserve”) in amounts that were intended to be sufficient to cover, among other things, storm-recovery costs associated with most but not all storm seasons. Consistent with past Commission policy and practice, in cases of extreme weather and restoration costs, a special assessment or surcharge is an appropriate means to recover the cost of storm restoration in excess of the Reserve. A long period of relatively mild hurricane seasons allowed the Reserve to grow to $354 million prior to being depleted as a result of the unprecedented 2004 storm season, leaving the Company’s Reserve with a large deficit to recover through a special assessment. Pursuant to FPSC Order No. PSC-05-0937-FOF-EI, issued September 21, 2005, in Docket 041291-EI, FPL’s prudently incurred 2004 storm season costs in excess of the Reserve currently are being recovered through a monthly storm recovery surcharge equal to $1.65 for the typical residential bill (1,000 kilowatt-hours (“kWh”)) (“2004 Storm Restoration Surcharge”).

In its base rate proceeding last year in Docket No. 050045-EI, FPL proposed to increase base rates by an amount sufficient to cover the expected average annual cost of storm restoration plus an amount to replenish the Reserve in a reasonable period of time. The parties to the Stipulation and Settlement Agreement in Docket No. 050045-EI (“Settlement Agreement”) elected instead to hold base rates constant by providing for the recovery of all such costs outside of the Company’s base rates. Replenishment of the Reserve and recovery of the cost of restoring power in the wake of storms was to be accomplished through means of a new financing vehicle approved by the Florida Legislature during its 2005 session and codified in Section 366.8260, Florida Statutes (2005), and/or through the more conventional mechanism of a special assessment or surcharge. In approving the Settlement Agreement, however, the Commission expressed concern about being left without a more definite course of action to replenish the Reserve and strongly encouraged the Company to propose a plan at the earliest opportunity. FPL therefore files this petition in response to its commitment to the Commission to pursue a plan to replenish its Reserve within six months of the Commission’s approval of the Settlement Agreement. See Order No. PSC-05-0902-S-EI, Docket Nos. 050045-EI, 050188-EI (issued September 14, 2005), at p. 5.

Indeed, FPL and its customers were subjected to another extremely destructive hurricane season in 2005. During 2005, FPL and its customers were affected by four hurricanes – Dennis, Katrina, Rita and Wilma. All four of the hurricanes impacted the most densely populated areas in FPL’s service territory, Palm Beach, Broward and Miami-Dade counties, where 60% of FPL’s customers reside. Hurricane Katrina made landfall near the Miami-Dade and Broward county line. Hurricane Wilma made landfall on the southwest coast of Florida and exited near Palm Beach, significantly impacting Palm Beach, Broward and Miami-Dade counties and causing more outages for FPL than any other previous storm. In addition to the damage to FPL’s infrastructure, Hurricane Wilma caused significant damages to the communities that the Company serves. It has been reported that Hurricane Wilma could prove to be the worst storm to impact Miami since August 1992, when Hurricane Andrew caused more than $25 billion in damage. The American Red Cross also has reported that over 27,000 dwellings were destroyed or rendered temporarily unlivable, an indication of the destruction caused by Hurricane Wilma. Hurricanes Dennis and Rita, while not making landfall in FPL’s territory, traveled near enough for their outer bands to cause significant outages, particularly in Miami-Dade and Broward counties.

Of the four storms impacting FPL’s service territory last year, the two storms inflicting the vast majority of damage to FPL’s system in 2005 occurred subsequent to execution of the Settlement Agreement. Hurricane Wilma, a massive storm and the most destructive event of the season, swept across the most heavily populated areas within FPL’s service territory and resulted in widespread damage to property and infrastructure, including huge portions of FPL’s transmission and distribution system. In the heavily populated counties of Dade, Broward, and Palm Beach, 99% of our customers were without power once the storm passed. Unlike prior storms, Hurricane Wilma inflicted damage not just to distribution systems, but to transmission structures and substations throughout FPL’s service territory. To repair the damage and restore service to more than 3.2 million customers in 21 counties, over 19,000 restoration workers, including approximately 9,200 foreign utility and other contractor personnel, from 36 states and Canada were deployed by FPL. A restoration team of this size had never before been assembled in FPL’s 80 year history.

FPL’s planning and execution before, during and after the 2005 storms was focused upon safely restoring the greatest number of customers in the least amount of time to return the communities the Company serves to normalcy. For the four 2005 storms, approximately 5.3 million customers required power restoration. For Hurricanes Dennis and Rita, customers were 100% restored within three and two days, respectively. For Hurricane Katrina, 77% of the customers affected were restored in three days, 95% in five days and 100% in eight days. For Hurricane Wilma, FPL restored service to over two million customers, or 65% of all affected customers by the fifth day, and 100% were restored by the eighteenth day. The high percentages accomplished in the first few days in each storm result from FPL’s consistently applied restoration strategy – to restore devices that serve the largest number of customers first. FPL further refined its processes and effectively managed field operations, while acquiring an extraordinary number of workers and managing many staging sites. As a result, FPL restored service to its customers and repaired its facilities in an expeditious and prudent manner. FPL submits that its 2005 storm-recovery costs as noted herein and described more fully in the Company’s supporting testimony are reasonable and prudent, “with reference to the general public interest in, and the scope of effort required to provide, the safe and expeditious restoration of electric service”, as provided for in Section 366.8260(2)(b)(1)(b), Florida Statutes.

As a result of the devastating impact of the 2005 storm season, in addition to the need to replenish the Reserve to a reasonable level for future storm seasons, FPL and its customers are left with an even larger deficit in the Reserve and a more urgent need to remedy the situation in anticipation of yet another potentially active storm season. Total estimated storm-recovery costs for 2005 are $906.4 million, including $721.7 million due to Hurricane Wilma, increasing the Reserve deficiency to a level of approximately $816 million and leaving a deficit balance in the Reserve in excess of $1.1 billion.

Historically, there have been periods of higher and lower hurricane activity. A growing body of climatological evidence suggests that the Atlantic basin has entered a more active period for hurricane formation. If true, an adequate and timely replenished Reserve is even more critical to meet the needs of another potentially active storm season in 2006.

As contemplated by Section 366.8260(2)(b)1.b., FPL requests that the Commission approve recovery of FPL’s prudently incurred storm-recovery costs related to the 2005 storm season. Such recovery will enable FPL to continue to fulfill its statutory obligation to serve its customers by safely and expeditiously restoring power in the event of storms, with FPL being timely reimbursed for its reasonable and prudently incurred storm-related costs. Further, such approval will reduce regulatory uncertainty associated with storm-related expenditures.

FPL requests that the Commission issue a Financing Order substantially in the form attached for FPL to implement storm–recovery financing as provided for in Section 366.8260. Specifically, FPL requests that the Commission approve the issuance of storm-recovery bonds in the amount of up to $1,050 million, enabling: (i) recovery of the remaining unrecovered balance of the 2004 storm costs; (ii) recovery of the 2005 prudently incurred storm costs; (iii) replenishment of the Reserve to a level of approximately $650 million; and (iv) recovery of the upfront bond issuance costs. Bonds are issued for the after-tax value of storm restoration costs to recognize the tax benefit received when storm restoration costs are deducted for income tax purposes. Thus, the $1,039 (approximately) million of bond proceeds available after the payment of upfront bond issuance costs, provides approximately $638 million to reimburse the Company for unrecovered storm costs and approximately $400 million to replenish the fund (the after-tax equivalent of a $650 million Reserve). A summary of the costs subject to FPL’s request in this Petition are set forth in the attached document identified as Exhibit A.

In order to facilitate review of the matters presented in this Petition and to help ensure that the requisite elements needed to satisfy rating agency conditions, obtain favorable tax treatment, and otherwise ensure the benefits associated with the issuance of storm-recovery bonds, FPL has attached a proposed form of financing order to this Petition as Exhibit B (“Financing Order”). FPL requests issuance of the Financing Order substantially in the form proposed.

As explained in this Petition and FPL’s supporting testimony, approving such Financing Order will enable FPL to cause the issuance of storm-recovery bonds to recover in a timely manner the storm-recovery costs that the Company incurred and advanced on behalf of its customers during the highly destructive back-to-back 2004 and 2005 storm seasons. The unrecovered portion of the 2004 storm-recovery costs also would be included for recovery in the subject financing, as well as FPL’s prudently incurred 2005 storm-recovery costs. Thus, the 2004 Storm Restoration Surcharge would be terminated on the effective date of the new cost recovery mechanism implemented pursuant to the Financing Order and upon issuance of the storm-recovery bonds. Approving the requested Financing Order to recover storm-recovery costs incurred also will enable FPL to replenish the Reserve to a level of approximately $650 million. Although a Reserve of $650 million is not necessarily what the Company would project as an adequate Reserve level going forward, weighing a number of factors including (i) an expected average annual cost for windstorm losses of approximately $73.7 million as determined by FPL’s outside expert Mr. Harris, (ii) the possibility that Florida is in the midst of a much more active hurricane period relative to average levels of activity over the much longer term, (iii) the potentially diminished availability of non-T&D property insurance, (iv) the impact of the recent severe and unprecedented storm seasons on customer bills in the near term, and (v) the opportunity to revisit this issue in future proceedings, establishing a Reserve level of approximately $650 million is reasonable at this time.

The financing that would be implemented pursuant to Section 366.8260 would provide customers with the benefit of lower cost long-term financing than otherwise would be available. From the point of view of FPL’s customers, an issuance of storm-recovery bonds as proposed can reasonably be expected to result in a lower, relatively constant monthly storm charge of $1.58 (based on recent market conditions) for the typical residential bill (1,000 kWh) over an approximate twelve-year period, in lieu of continuing the 2004 Storm Restoration Surcharge plus other surcharges that would be needed to recover prudently incurred 2005 storm-recovery costs and begin to replenish the Reserve over a reasonable period of time. Moreover, assuming timely implementation of the proposed storm recovery financing, customers will have the benefit of a funded Reserve being immediately available during the peak of the 2006 storm season. The same cannot be said for the more traditional method of building the Reserve through base rate accruals and/or surcharges. In the past, FPL and its customers have had to experience extended periods of abnormally low storm activity for the base rate accrual to build the Reserve to a level that, nevertheless, proved to be well short of what was necessary to respond to the 2004 storm season, let alone back-to-back seasons of the magnitude experienced. The same also would be true of a surcharge unless it were sufficiently large to cover much more than just expected annual losses.

The storm cost recovery described in this Petition, and associated financing costs, would be paid for pursuant to an approximate twelve-year Storm Bond Repayment Charge that would be applied on a per kWh basis to all applicable customer classes. FPL customers would pay for any tax liabilities associated with the collection of the Storm Bond Repayment Charge through a similarly collected Storm Bond Tax Charge, to the extent such tax liabilities are not otherwise recovered from customers through other rates or charges. In connection with this filing, FPL is submitting proposed Storm Bond Repayment Charge and Storm Bond Tax Charge tariff sheets that will closely approximate the final figures, barring significant changes in the terms of an issuance of storm-recovery bonds. The Storm Bond Repayment Charge and Storm Bond Tax Charge together comprise the “Storm Charge.” The existing 2004 Storm Restoration Surcharge would be terminated simultaneously with the effective date of the proposed tariff sheets.

Advantages of proposed storm recovery financing include recovery of the 2005 storm-recovery costs and immediate replenishment of the Reserve by approximately $650 million during the 2006 hurricane season. Customers also would pay a lower per kWh charge over a longer period of time relative to the 2004 Storm Restoration Surcharge which would be discontinued.

In light of the size of the current deficit and the need to begin to reduce the deficit and rebuild the Reserve to prepare for another potentially active storm season, the Company requests that as part of the Financing Order the Commission approve a surcharge to be applied to bills rendered on and after August 15, 2006 to recover the 2005 storm-restoration costs over approximately three years (or until the applicable revenue requirements have been recovered) in the event the issuance of storm-recovery bonds is delayed for any reason. The monthly impact to residential customers of this surcharge is currently estimated to be $2.98 for a typical (1,000 kWh) residential bill based on current estimates for 2005 storm restoration costs. This surcharge would only be implemented in the event of a delay in issuing the storm-recovery bonds and it would be discontinued upon issuance. The amount of storm-recovery bonds issued would be adjusted to reflect collections pursuant to this surcharge, thus commensurately reducing the resulting Storm Charge.

Conversely, if the Commission declines to issue the Financing Order in substantially the form of Exhibit B, and/or does not grant the associated approvals for FPL to implement storm recovery financing under Section 366.8260, FPL requests in the alternative that the Commission approve a surcharge effective for bills rendered on and after June 15, 2006 in the amount and for such period as described more fully below to recover its prudently incurred storm costs during 2005 and also to begin to replenish the Reserve to a reasonable level. This surcharge would be in addition to the 2004 Storm Restoration Surcharge which would remain in effect. In connection with the recovery of such costs through a surcharge, FPL likewise requests approval of its prudently incurred storm-recovery costs related to the 2005 storm season. If the Commission approves FPL’s alternative request, FPL would submit tariff sheets for administrative approval.

FPL requests that the Commission consider and approve the relief requested in this petition consistent with the 135-day timeline set forth in Section 366.8260(2)(b)1.b. in order that storm-recovery bonds may be issued, and that the purposes of this Petition be achieved. This would allow the establishment of a Reserve of approximately $650 million, in preparation for the 2006 storm season or, alternatively, timely implementation of a surcharge to recover prudently incurred storm-recovery costs in connection with the 2005 storm season and to begin to replenish the Reserve.

FPL’s requests in this petition do not address future storm damage in excess of the Reserve level, irrespective of the method approved by the Commission in this proceeding. FPL would petition the Commission at a later time for recovery of such excess amounts, consistent with past Commission policy and decisions, in the event that expenditures exceed the Reserve balance.

In support of this Petition, FPL states as follows:



Jurisdiction and Regulatory Background

  1. FPL is a public utility subject to the jurisdiction of the Commission under Chapter 366, Florida Statutes (2005). FPL’s General Offices are located at 9250 West Flagler Street, Miami, FL 33174.

  2. Any pleading, motion, notice, order or other document required to be served upon

the petitioner or filed by any party to this proceeding should be served upon the following individuals:

William G. Walker, III R. Wade Litchfield

Vice President Associate General Counsel

Florida Power & Light Company Florida Power & Light Company

215 South Monroe Street 700 Universe Boulevard

Suite 810 Juno Beach, Florida 33408-0420

Tallahassee, FL 32301-1859 (561) 691-7101

(850) 521-3900 (561) 691-7135 (telecopier)

(850) 521-3939 (telecopier) Wade_Litchfield@fpl.com

Bill_Walker@fpl.com




  1. FPL is not aware of any disputed issue of material fact. This Petition is not filed in response to any agency decision.

  2. FPL serves approximately 4.3 million retail customers in its service area in Florida. Its service area comprises approximately 27,000 square miles in 35 of the state's 67 counties, encompassing the cities of Daytona Beach, Ft. Lauderdale, Ft. Myers, Miami, Naples and West Palm Beach and other densely populated areas on the East and West coasts of Florida. Further, FPL serves a number of less densely populated areas, including all or portions of Martin, St. Lucie, Indian River, Brevard, Charlotte, Desoto, Columbia, Highlands, Okeechobee, Seminole and Union Counties.

  3. FPL has established a Reserve pursuant to prior Commission orders and consistent with Rule 25-6.0143, Florida Administrative Code. The Commission has previously agreed that the establishment of the Reserve provides an appropriate means of self-insurance, particularly where no reasonable commercial insurance market exists to cover the costs of repairing and restoring its transmission and distribution system in the event of a hurricane, storm damage or other natural disaster. See In Re: Petition for authority to recover prudently incurred storm recovery costs related to 2004 storm season that exceed storm reserve balance, by Florida Power & Light Company, Docket No. 041291-EI, Order No. PSC-05-0937-FOF-EI (issued September 21, 2005)2; In Re: Petition to implement a self-insurance mechanism for storm damage to transmission and distribution system and to resume and increase annual contribution to storm and property insurance reserve fund by Florida Power & Light Company, Docket No. 930405-EI, Order Nos. PSC-93-0918-FOF-EI (issued: June 17, 1993)3 and PSC 95-0264-FOF-EI (issued: Feb. 27, 1995);4 In Re: Petition for authorization to increase the annual storm fund accrual commencing January 1, 1995 to $20.3 million; to add approximately $51.3 million of recoveries for damage due to Hurricane Andrew and the March 1993 Storm; and to re-establish the storm reserve for the costs of Hurricane Erin by increasing the storm reserve and charging to expense approximately $5.3 million, by Florida Power & Light Company, Docket No. 951167-EI, Order No. PSC 95-1588-FOF-EI (issued: Dec. 27, 1995);5 In Re: Petition for authority to increase annual storm fund accrual commencing January 1, 1997, to $35 million by Florida Power & Light Company, Docket No. 971237-EI, Order No. 98-0953-FOF-EI (issued: July 14, 1998).6

  4. Pursuant to these and other Commission orders, FPL has been operating under a self-insurance plan for storm-related costs in which the accrual and Reserve were intended to cover costs due to most, but not all, storm events. In the event that the Reserve proved to be inadequate due to an extraordinary event or storm season, it was expressly contemplated that FPL would have the ability to seek recovery of reasonable and prudently incurred storm-recovery costs in excess of the Reserve. Funds allocated to the Reserve are accumulated by FPL in Account No. 228.1, Accumulated Provision for Property Insurance, which is intended to provide cash reserves necessary to cover the costs of damage, net of insurance proceeds.

  5. In its application for a base rate increase in Docket No. 050045-EI, FPL had proposed to increase the annual Reserve accrual in base rates to $120 million. The total accrual was comprised of an amount approximating the expected annual storm losses, plus an amount to contribute toward restoring the Reserve balance to a level of $500 million. The base rate proceeding was resolved pursuant to the Settlement Agreement negotiated and signed by parties to the proceeding and approved by the Commission which, among other matters, addressed the issues of storm cost recovery and the replenishment of the Reserve. Order No. PSC-05-0902-S-EI, Docket Nos. 050045-EI, 05-0188-EI (Issued September 14, 2004), at p. 5.

  6. With respect to storm costs, the Settlement Agreement (a) suspends the then-current base rate accrual of $20.3 million effective as of January 1, 2006; (b) provides that FPL will be entitled to recover prudently incurred storm-recovery costs and replenish the Reserve balance to a level to be approved by the Commission; and (c) allows recovery of prudently incurred storm-recovery costs and replenishment of the Reserve through charges to customers incremental to base rates, through a storm-recovery charge established through Section 366.8260, and/or another form of surcharge. Id.

  7. While approving the storm cost provisions as part of the overall settlement, Commissioners expressed concern over the continuing deficit in the Reserve and at the prospect of concluding the rate proceeding without a current plan to replenish the Reserve to a reasonable level. The Commission requested, and FPL committed, to address those concerns within six months of the August 24, 2005 approval of the Settlement Agreement. Id. This Petition seeks to address these concerns, after two exceptionally strong and destructive storm seasons in 2004 and 2005, with the objective of proposing a sound approach to recovering such costs and restoring the Reserve balance to a reasonable level to meet the needs of the 2006 storm season.

  8. Traditional methods for recovering storm costs and establishing a Reserve, discussed above, include an accrual in base rates that is contributed to the Reserve and implementation of a special assessment or surcharge to recover storm costs in excess of amounts in the Reserve. Most recently, in Order No. PSC 05-0937-FOF-EI, issued September 21, 2005, in Docket No. 041291-EI, the Commission approved the initiation of a surcharge to recover the prudently incurred restoration costs in excess of the Reserve balance related to the 2004 storm season.

  9. At the date of this Petition, FPL has a large unrecovered balance associated with the 2004 storm-recovery costs approved by the Commission in the above-referenced order. This is because the surcharge approved by the Commission to recover the costs associated with the 2004 storms has not been in place long enough to recover all of the costs approved by the Commission in that proceeding. FPL estimates the unrecovered balance of 2004 costs will be $212 million (jurisdictional) as of July 31, 2006.

12. With respect to 2005 storm-recovery costs, FPL has incurred substantial costs to restore service to customers due to Hurricanes Dennis, Katrina, Rita and Wilma. Because FPL’s Reserve had a very large negative balance as a result of the 2004 storms, FPL advanced its funds to pay for 2005 storm-recovery costs, subject to reimbursement by customers. Under the traditional approach to storm cost recovery, in circumstances such as the present where the Reserve balance is negative and there are substantial storm costs to recover, FPL would petition the Commission to recover the prudently incurred 2005 storm-recovery costs through the establishment of a special assessment or surcharge sufficient to recover from customers the 2005 storm-recovery costs, as well as to begin to replenish the Reserve to a reasonable level to meet future storm restoration needs.

13. Section 366.8260 provides an alternative method for recovering storm restoration costs, as well as replenishing the Reserve. Rather than including an accrual in base rates (which is discontinued as of January 1, 2006 pursuant to the Settlement Agreement), or petitioning for an additional surcharge for 2005 storm-recovery costs and Reserve replenishment, accompanying the existing surcharge for 2004 storm-recovery costs, FPL’s primary request in this proceeding is that the Commission issue a Financing Order in substantially the form provided, authorizing the issuance of bonds sufficient to pay for all of the unrecovered 2004 and 2005 storm-recovery costs, to replenish the Reserve, and to pay upfront bond issuance costs.

14. If approved by the Commission in this proceeding, the storm-recovery bonds authorized by the Financing Order would be structured in the manner provided for in Section 366.8260, thus enabling the bonds to achieve a higher credit rating and lower cost than FPL’s other long-term financing options, and significantly mitigating rate impacts, compared to the more traditional method of recovery through a surcharge. Thus, issuing storm-recovery bonds as proposed, pursuant to Section 366.8260, would permit payment for all of the unrecovered 2004 and 2005 storm-recovery costs, as well as the costs of replenishing the Reserve to a reasonable level through a low, relatively constant charge to customers over an approximate twelve-year period, rather than through the continuation of the existing 2004 Storm Restoration Surcharge, and implementation of a new surcharge to recover the 2005 storm restoration costs and to begin to replenish the Reserve.

15. However, if the Commission determines that FPL should not issue bonds to recover the deficit in the Reserve and replenish the Reserve, the Company requests that the Commission approve an alternative and more traditional method of recovering storm-recovery costs and replenishing the Reserve through a storm surcharge. Specifically, FPL’s alternative request would consist of a surcharge to recover FPL’s 2005 storm-recovery costs over a period of approximately three years and a storm surcharge sufficient to collect $650 million over a three-year period to apply toward replenishment of the Reserve. FPL would ask that the proposed surcharge alternative be implemented for bills rendered on and after June 15, 2006. This new monthly charge would be $5.19 for a typical (1,000 kWh) residential bill. In combination with the 2004 Storm Restoration Surcharge, which would remain in effect, this would produce a total monthly storm-related charge of $6.84 on customer bills.

16. In light of the size of the current deficit and the need to begin to reduce the deficit and rebuild the Reserve to prepare for another potentially active storm season, the Company recommends that in the Financing Order, the Commission approve a surcharge to be applied to bills rendered on and after August 15, 2006 to recover the 2005 storm-restoration costs over approximately three years (or until the applicable revenue requirements have been recovered) in the event the issuance of storm-recovery bonds is delayed for any reason. The monthly impact to residential customers of this surcharge is currently estimated to be $2.98 for a typical (1,000 kWh) residential bill based on current estimates for 2005 storm restoration costs. The surcharge would be discontinued when the storm-recovery bonds are issued. The amount of storm-recovery bonds issued would be adjusted for the impact of collections of this surcharge.

17. If the Commission declines to issue the Financing Order in substantially the form of Exhibit B, and/or does not grant the associated approvals for FPL to implement storm recovery financing under Section 366.8260, FPL requests in the alternative that the Commission approve a surcharge effective for bills rendered on and after June 15, 2006 in the amount and for such period as described more fully below to recover its prudently incurred storm costs during 2005 and also to begin to replenish the Reserve to a reasonable level. This surcharge would be in addition to the 2004 Storm Restoration Surcharge which would remain in effect. In connection with the recovery of such costs through a surcharge, FPL likewise requests approval of its prudently incurred storm-recovery costs related to the 2005 storm season. If the Commission approves FPL’s alternative request, FPL would submit tariff sheets for administrative approval prior to the effective date of the surcharge.

18. The balance of this petition provides the (i) information required to be provided in support of FPL’s request for a financing order pursuant to Section 366.8260; (ii) information relating to FPL’s alternative request for the implementation of surcharges; as well as (iii) information concerning FPL’s prudently incurred storm-recovery costs for the 2005 season, for which FPL seeks approval in this proceeding as provided for in Section 366.8260(2)(b)1.